Washington Preliminary Notice Guide: Notice to Owner (RCW 60.04.031)

Everything specialty trade subcontractors need to know about serving a compliant preliminary notice in Washington (WA), required recipients, and preserving full mechanics lien rights.

Statutory Notice FormNotice to Owner (RCW 60.04.031)
Notice Deadline Window60 Days (From First Work)
Final Lien Recording Cutoff90 Days (Last Work)
Have an active job in Washington? Calculate your exact calendar cutoff dates and export `.ics` phone reminders.
Open Washington Date Calculator →

1. When Must a Subcontractor Send Notice in Washington?

In Washington, subcontractors and material suppliers who do not contract directly with the property owner must serve a Notice to Owner (RCW 60.04.031) within 60 days of first furnishing labor or materials to the job site.

Key Statutory Rule: Commercial subs must give notice within 60 days of first furnishing.

2. Who Must Receive the Notice & Proof of Service

Serve via USPS Certified Mail with Return Receipt Requested (or statutory overnight courier) to the Property Owner, General Contractor, and Construction Lender (if applicable). Retain the stamped USPS mailing receipt as proof of timely service.

  • Property Owner: Listed on the building permit, Notice of Commencement, or county tax assessor parcel record.
  • Prime / General Contractor: The entity holding the direct contract with the owner.
  • Construction Lender (if any): Protects priority if a bank or lender is financing the commercial build.

3. Essential Information to Include in Your Notice

To avoid technical invalidation in Washington, verify that your notice clearly states:

  • Your company's legal business name, address, and contact information.
  • Name and address of the General Contractor or party who hired you.
  • Street address and legal/parcel description of the job site.
  • Clear description of the trade labor, services, or materials furnished.
  • Estimated or contracted dollar value of your subcontract scope.
Past-Due Invoice?

Washington Notice of Intent to Lien Generator

If your preliminary notice window is satisfied and an invoice is overdue, generate a formal Certified Mail Notice of Intent to Lien before your 90-day cutoff expires.

Generate Demand Letter PDF →
Submitting a Pay App?

Conditional Lien Waiver Generator

Never sign an unconditional waiver before funds clear. Generate a safe Conditional Waiver for your progress draw or final retainage payout.

Generate Lien Waiver PDF →

Preliminary Notice Requirements by State (All 50 States + D.C.)