Alabama Mechanics Lien & Preliminary Notice Deadline Calculator
Calculate exact statutory cutoff dates for commercial subcontractors in Alabama (AL) under Notice of Intent to Claim Lien (§ 35-11-218) and export calendar reminder alerts.
Alabama (AL) Mechanics Lien Deadline Calculator
Statute Reference: Notice of Intent to Claim Lien (§ 35-11-218)
Subcontractors must deliver formal written notice to owner prior to filing.
Calculated 120 calendar days from your last day furnishing labor or materials.
Does Alabama require a preliminary notice before filing a mechanics lien?
Alabama does not mandate a universal early preliminary notice at the start of work, though formal notice prior to filing may still apply. Subcontractors must deliver formal written notice to owner prior to filing.
How many days do you have to file a mechanics lien in Alabama?
Under Notice of Intent to Claim Lien (§ 35-11-218), a Alabama mechanics lien must generally be filed within 120 days from the last day labor or materials were furnished to the project.
Pricing your next Alabama commercial bid?
Calculate true payroll burden, overhead recovery, and gross profit margin before submitting your proposal.