Tennessee Mechanics Lien & Preliminary Notice Deadline Calculator
Calculate exact statutory cutoff dates for commercial subcontractors in Tennessee (TN) under Notice of Nonpayment (Tenn. Code § 66-11-145) and export calendar reminder alerts.
Tennessee (TN) Mechanics Lien Deadline Calculator
Statute Reference: Notice of Nonpayment (Tenn. Code § 66-11-145)
Must deliver notice within 90 days of the end of each month unpaid.
Calculated 90 calendar days from overall project completion.
When is a preliminary notice due in Tennessee?
In Tennessee, specialty subcontractors must serve a Notice of Nonpayment (Tenn. Code § 66-11-145) within 90 days of last furnishing labor or materials. Must deliver notice within 90 days of the end of each month unpaid.
How many days do you have to file a mechanics lien in Tennessee?
Under Notice of Nonpayment (Tenn. Code § 66-11-145), a Tennessee mechanics lien must generally be filed within 90 days from project completion.