Colorado Mechanics Lien & Preliminary Notice Deadline Calculator
Calculate exact statutory cutoff dates for commercial subcontractors in Colorado (CO) under Notice of Intent to File Lien (C.R.S. § 38-22-109) and export calendar reminder alerts.
Colorado (CO) Mechanics Lien Deadline Calculator
Statute Reference: Notice of Intent to File Lien (C.R.S. § 38-22-109)
Must serve Notice of Intent at least 10 days before recording lien.
Calculated 120 calendar days from your last day furnishing labor or materials.
When is a preliminary notice due in Colorado?
In Colorado, specialty subcontractors must serve a Notice of Intent to File Lien (C.R.S. § 38-22-109) within 10 days of invoice or pre-filing notice date. Must serve Notice of Intent at least 10 days before recording lien.
How many days do you have to file a mechanics lien in Colorado?
Under Notice of Intent to File Lien (C.R.S. § 38-22-109), a Colorado mechanics lien must generally be filed within 120 days from the last day labor or materials were furnished to the project.