Virginia Mechanics Lien & Preliminary Notice Deadline Calculator

Calculate exact statutory cutoff dates for commercial subcontractors in Virginia (VA) under Memorandum of Mechanic’s Lien (Va. Code § 43-4) and export calendar reminder alerts.

Virginia (VA) Mechanics Lien Deadline Calculator

Statute Reference: Memorandum of Mechanic’s Lien (Va. Code § 43-4)

90-Day Filing Window
Virginia Preliminary Notice Deadline
Not Statutorily Mandated

Must be filed within 90 days. Virginia enforces a strict 150-day lookback rule.

Virginia Final Mechanics Lien Cutoff
Enter Last Work Date

Calculated 90 calendar days from your last day furnishing labor or materials.

Get Automated SMS Alerts ($19/mo) →

Does Virginia require a preliminary notice before filing a mechanics lien?

Virginia does not mandate a universal early preliminary notice at the start of work, though formal notice prior to filing may still apply. Must be filed within 90 days. Virginia enforces a strict 150-day lookback rule.

Read Step-by-Step Virginia Preliminary Notice Guide →

How many days do you have to file a mechanics lien in Virginia?

Under Memorandum of Mechanic’s Lien (Va. Code § 43-4), a Virginia mechanics lien must generally be filed within 90 days from the last day labor or materials were furnished to the project.

Generate a Virginia Notice of Intent to Lien Letter →
Free Subcontractor Estimating Suite

Pricing your next Virginia commercial bid?

Calculate true payroll burden, overhead recovery, and gross profit margin before submitting your proposal.

Mechanics Lien Deadlines by State (All 50 States + D.C.)