Home/Florida Lien Deadlines

Florida Mechanics Lien & Preliminary Notice Deadline Calculator

Calculate exact statutory cutoff dates for commercial subcontractors in Florida (FL) under Notice to Owner (NTO) (Fla. Stat. § 713.06) and export calendar reminder alerts.

Florida (FL) Mechanics Lien Deadline Calculator

Statute Reference: Notice to Owner (NTO) (Fla. Stat. § 713.06)

90-Day Filing Window
Florida Preliminary Notice Deadline
Enter First Work Date

Must be served within 45 days of first work or prior to final payment.

Florida Final Mechanics Lien Cutoff
Enter Last Work Date

Calculated 90 calendar days from your last day furnishing labor or materials.

Get Automated SMS Alerts ($19/mo) →

When is a preliminary notice due in Florida?

In Florida, specialty subcontractors must serve a Notice to Owner (NTO) (Fla. Stat. § 713.06) within 45 days of first furnishing labor or materials. Must be served within 45 days of first work or prior to final payment.

Read Step-by-Step Florida Preliminary Notice Guide →

How many days do you have to file a mechanics lien in Florida?

Under Notice to Owner (NTO) (Fla. Stat. § 713.06), a Florida mechanics lien must generally be filed within 90 days from the last day labor or materials were furnished to the project.

Generate a Florida Notice of Intent to Lien Letter →
Free Subcontractor Estimating Suite

Pricing your next Florida commercial bid?

Calculate true payroll burden, overhead recovery, and gross profit margin before submitting your proposal.