Mississippi Mechanics Lien & Preliminary Notice Deadline Calculator

Calculate exact statutory cutoff dates for commercial subcontractors in Mississippi (MS) under Pre-Lien Notice to Owner (Miss. Code § 85-7-405) and export calendar reminder alerts.

Mississippi (MS) Mechanics Lien Deadline Calculator

Statute Reference: Pre-Lien Notice to Owner (Miss. Code § 85-7-405)

90-Day Filing Window
Mississippi Preliminary Notice Deadline
Enter First Work Date

Subcontractors must provide notice to owner if GC has not filed Commencement.

Mississippi Final Mechanics Lien Cutoff
Enter Last Work Date

Calculated 90 calendar days from your last day furnishing labor or materials.

Get Automated SMS Alerts ($19/mo) →

When is a preliminary notice due in Mississippi?

In Mississippi, specialty subcontractors must serve a Pre-Lien Notice to Owner (Miss. Code § 85-7-405) within 30 days of first furnishing labor or materials. Subcontractors must provide notice to owner if GC has not filed Commencement.

Read Step-by-Step Mississippi Preliminary Notice Guide →

How many days do you have to file a mechanics lien in Mississippi?

Under Pre-Lien Notice to Owner (Miss. Code § 85-7-405), a Mississippi mechanics lien must generally be filed within 90 days from the last day labor or materials were furnished to the project.

Generate a Mississippi Notice of Intent to Lien Letter →
Free Subcontractor Estimating Suite

Pricing your next Mississippi commercial bid?

Calculate true payroll burden, overhead recovery, and gross profit margin before submitting your proposal.

Mechanics Lien Deadlines by State (All 50 States + D.C.)