Utah Mechanics Lien & Preliminary Notice Deadline Calculator
Calculate exact statutory cutoff dates for commercial subcontractors in Utah (UT) under Preliminary Notice via SCR (Utah Code § 38-1a-501) and export calendar reminder alerts.
Utah (UT) Mechanics Lien Deadline Calculator
Statute Reference: Preliminary Notice via SCR (Utah Code § 38-1a-501)
Must be filed online with the State Construction Registry (SCR) within 20 days.
Calculated 180 calendar days from your last day furnishing labor or materials.
When is a preliminary notice due in Utah?
In Utah, specialty subcontractors must serve a Preliminary Notice via SCR (Utah Code § 38-1a-501) within 20 days of first furnishing labor or materials. Must be filed online with the State Construction Registry (SCR) within 20 days.
How many days do you have to file a mechanics lien in Utah?
Under Preliminary Notice via SCR (Utah Code § 38-1a-501), a Utah mechanics lien must generally be filed within 180 days from the last day labor or materials were furnished to the project.