Maine Mechanics Lien & Preliminary Notice Deadline Calculator

Calculate exact statutory cutoff dates for commercial subcontractors in Maine (ME) under Notice of Lien Claim (10 M.R.S. § 3253) and export calendar reminder alerts.

Maine (ME) Mechanics Lien Deadline Calculator

Statute Reference: Notice of Lien Claim (10 M.R.S. § 3253)

90-Day Filing Window
Maine Preliminary Notice Deadline
Not Statutorily Mandated

Must be preserved by filing certificate within 90 days of last work.

Maine Final Mechanics Lien Cutoff
Enter Last Work Date

Calculated 90 calendar days from your last day furnishing labor or materials.

Get Automated SMS Alerts ($19/mo) →

Does Maine require a preliminary notice before filing a mechanics lien?

Maine does not mandate a universal early preliminary notice at the start of work, though formal notice prior to filing may still apply. Must be preserved by filing certificate within 90 days of last work.

Read Step-by-Step Maine Preliminary Notice Guide →

How many days do you have to file a mechanics lien in Maine?

Under Notice of Lien Claim (10 M.R.S. § 3253), a Maine mechanics lien must generally be filed within 90 days from the last day labor or materials were furnished to the project.

Generate a Maine Notice of Intent to Lien Letter →
Free Subcontractor Estimating Suite

Pricing your next Maine commercial bid?

Calculate true payroll burden, overhead recovery, and gross profit margin before submitting your proposal.

Mechanics Lien Deadlines by State (All 50 States + D.C.)