Connecticut Mechanics Lien & Preliminary Notice Deadline Calculator
Calculate exact statutory cutoff dates for commercial subcontractors in Connecticut (CT) under Notice of Intent to Claim Lien (Conn. Gen. Stat. § 49-34) and export calendar reminder alerts.
Connecticut (CT) Mechanics Lien Deadline Calculator
Statute Reference: Notice of Intent to Claim Lien (Conn. Gen. Stat. § 49-34)
Must be served on property owner within 90 days after ceasing labor.
Calculated 90 calendar days from your last day furnishing labor or materials.
Does Connecticut require a preliminary notice before filing a mechanics lien?
Connecticut does not mandate a universal early preliminary notice at the start of work, though formal notice prior to filing may still apply. Must be served on property owner within 90 days after ceasing labor.
How many days do you have to file a mechanics lien in Connecticut?
Under Notice of Intent to Claim Lien (Conn. Gen. Stat. § 49-34), a Connecticut mechanics lien must generally be filed within 90 days from the last day labor or materials were furnished to the project.