Connecticut Mechanics Lien & Preliminary Notice Deadline Calculator

Calculate exact statutory cutoff dates for commercial subcontractors in Connecticut (CT) under Notice of Intent to Claim Lien (Conn. Gen. Stat. § 49-34) and export calendar reminder alerts.

Connecticut (CT) Mechanics Lien Deadline Calculator

Statute Reference: Notice of Intent to Claim Lien (Conn. Gen. Stat. § 49-34)

90-Day Filing Window
Connecticut Preliminary Notice Deadline
Not Statutorily Mandated

Must be served on property owner within 90 days after ceasing labor.

Connecticut Final Mechanics Lien Cutoff
Enter Last Work Date

Calculated 90 calendar days from your last day furnishing labor or materials.

Get Automated SMS Alerts ($19/mo) →

Does Connecticut require a preliminary notice before filing a mechanics lien?

Connecticut does not mandate a universal early preliminary notice at the start of work, though formal notice prior to filing may still apply. Must be served on property owner within 90 days after ceasing labor.

Read Step-by-Step Connecticut Preliminary Notice Guide →

How many days do you have to file a mechanics lien in Connecticut?

Under Notice of Intent to Claim Lien (Conn. Gen. Stat. § 49-34), a Connecticut mechanics lien must generally be filed within 90 days from the last day labor or materials were furnished to the project.

Generate a Connecticut Notice of Intent to Lien Letter →
Free Subcontractor Estimating Suite

Pricing your next Connecticut commercial bid?

Calculate true payroll burden, overhead recovery, and gross profit margin before submitting your proposal.

Mechanics Lien Deadlines by State (All 50 States + D.C.)