Oregon Mechanics Lien & Preliminary Notice Deadline Calculator

Calculate exact statutory cutoff dates for commercial subcontractors in Oregon (OR) under Notice of Right to a Lien (ORS 87.021) and export calendar reminder alerts.

Oregon (OR) Mechanics Lien Deadline Calculator

Statute Reference: Notice of Right to a Lien (ORS 87.021)

75-Day Filing Window
Oregon Preliminary Notice Deadline
Enter First Work Date

Notice must be delivered to owner within 8 days of first delivery.

Oregon Final Mechanics Lien Cutoff
Enter Last Work Date

Calculated 75 calendar days from your last day furnishing labor or materials.

Get Automated SMS Alerts ($19/mo) →

When is a preliminary notice due in Oregon?

In Oregon, specialty subcontractors must serve a Notice of Right to a Lien (ORS 87.021) within 8 days of first furnishing labor or materials. Notice must be delivered to owner within 8 days of first delivery.

Read Step-by-Step Oregon Preliminary Notice Guide →

How many days do you have to file a mechanics lien in Oregon?

Under Notice of Right to a Lien (ORS 87.021), a Oregon mechanics lien must generally be filed within 75 days from the last day labor or materials were furnished to the project.

Generate a Oregon Notice of Intent to Lien Letter →
Free Subcontractor Estimating Suite

Pricing your next Oregon commercial bid?

Calculate true payroll burden, overhead recovery, and gross profit margin before submitting your proposal.

Mechanics Lien Deadlines by State (All 50 States + D.C.)