District of Columbia Mechanics Lien & Preliminary Notice Deadline Calculator
Calculate exact statutory cutoff dates for commercial subcontractors in District of Columbia (DC) under Notice of Mechanics Lien (D.C. Code § 40-301.02) and export calendar reminder alerts.
District of Columbia (DC) Mechanics Lien Deadline Calculator
Statute Reference: Notice of Mechanics Lien (D.C. Code § 40-301.02)
Must file and serve on owner within 90 days of project completion.
Calculated 90 calendar days from overall project completion.
Does District of Columbia require a preliminary notice before filing a mechanics lien?
District of Columbia does not mandate a universal early preliminary notice at the start of work, though formal notice prior to filing may still apply. Must file and serve on owner within 90 days of project completion.
How many days do you have to file a mechanics lien in District of Columbia?
Under Notice of Mechanics Lien (D.C. Code § 40-301.02), a District of Columbia mechanics lien must generally be filed within 90 days from project completion.