Arkansas Mechanics Lien & Preliminary Notice Deadline Calculator
Calculate exact statutory cutoff dates for commercial subcontractors in Arkansas (AR) under Commercial Pre-Lien Notice (Ark. Code § 18-44-115) and export calendar reminder alerts.
Arkansas (AR) Mechanics Lien Deadline Calculator
Statute Reference: Commercial Pre-Lien Notice (Ark. Code § 18-44-115)
Subcontractors must serve notice to owner prior to or within 75 days.
Calculated 120 calendar days from your last day furnishing labor or materials.
When is a preliminary notice due in Arkansas?
In Arkansas, specialty subcontractors must serve a Commercial Pre-Lien Notice (Ark. Code § 18-44-115) within 75 days of first furnishing labor or materials. Subcontractors must serve notice to owner prior to or within 75 days.
How many days do you have to file a mechanics lien in Arkansas?
Under Commercial Pre-Lien Notice (Ark. Code § 18-44-115), a Arkansas mechanics lien must generally be filed within 120 days from the last day labor or materials were furnished to the project.