North Carolina Mechanics Lien & Preliminary Notice Deadline Calculator
Calculate exact statutory cutoff dates for commercial subcontractors in North Carolina (NC) under Notice to Lien Agent (G.S. 44A-11.2) and export calendar reminder alerts.
North Carolina (NC) Mechanics Lien Deadline Calculator
Statute Reference: Notice to Lien Agent (G.S. 44A-11.2)
Must notify Lien Agent within 15 days of first work to protect priority.
Calculated 120 calendar days from your last day furnishing labor or materials.
When is a preliminary notice due in North Carolina?
In North Carolina, specialty subcontractors must serve a Notice to Lien Agent (G.S. 44A-11.2) within 15 days of first furnishing labor or materials. Must notify Lien Agent within 15 days of first work to protect priority.
How many days do you have to file a mechanics lien in North Carolina?
Under Notice to Lien Agent (G.S. 44A-11.2), a North Carolina mechanics lien must generally be filed within 120 days from the last day labor or materials were furnished to the project.
Pricing your next North Carolina commercial bid?
Calculate true payroll burden, overhead recovery, and gross profit margin before submitting your proposal.